Construction Update 12-12-19
Park District The Abbot The last core pour is scheduled to be completed on Monday (12/16). Level 4 interior wall framing, and in-wall...
Construction Update 12-06-19
Park District The Abbot Installation of the wall panels on level 10 has been completed. Drywall installation on level 4 will begin early...
Construction Update 11-27-19
Park District The Abbot Installation of the wall panels on level 10 is finishing up. Mechanical, Electrical and Plumbing trades are on...
Construction Update 11-22-19
West Grand River Ave. Underground Utility Work Completed The contractor has finished the underground utility work and the west bound...
Construction Update 11-15-18
West Grand River Ave. Underground Utility Work and Lane Closures Beginning Monday (11/18) Project Map Due to weather delays the week of...
Construction Update 11-08-19
West Grand River Ave. Underground Utility Work and Lane Closures Beginning Monday (11/11) Underground utility work will continue in the...