MSUFCU Construction Update 7-22-2022

The mechanical and plumbing contractor is currently onsite working on layout and installing storm piping on the 7th floor. The HVAC contractor is also onsite working on rough in locations for duct work and overhead units. The framing contractor is working on the east elevation from top down, they are currently framing the 5th floor exterior. They also have a crew working on interior wall lay out and framing. The roofing contractor is currently on site working on the roof. We will be pouring our first slab on grade section mid-next-week.
Albert Ave. remains closed to through traffic. This closure will remain in effect through the summer and is expected to be removed prior to student move-in for Michigan State University. The lane closures on Abbot Rd. will remain in effect for the foreseeable future. The south access to the alley off Albert Ave. will be closed to vehicles and pedestrians for the duration of overhead work to help ensure safety. The alley is accessible from the north.