Construction Updates! September 10, 2021
City of East Lansing DDA Properties – 314, 328, and 334 Evergreen Granger will continue to backfill and establish the site and will...


Construction Updates! September 3, 2021
City of East Lansing DDA Properties – 314, 328, 334 Demolition of the foundation of 314 is ongoing and is anticipated to be completed...
Construction Update 08-27-21
08-27-21 MSUFCU 314, 328, 334 Evergreen Ave. Demolition of the buildings on 334 and 328 Evergreen Ave. has been completed. Demolition of...


Construction Updates: August 20, 2021
City of East Lansing Downtown Development Authority Properties The utility disconnects have been completed. Demolition of 334 and 328 has...


Construction Updates August 13, 2021
City of East Lansing, Downtown Development Authority Properties: 314, 328, 334 Evergreen The interior abatement is complete. Utilities...


News Release: Motorists Advised of Upcoming Abbot Road Closure
Media Contact: Scott House Director Department of Public Works (517) 337-9459 Motorists Advised of Upcoming Abbot Road Closure 20-161...

Construction Update 01-31-20
Park District The Abbot Drywall work continues on level 6 moving up to level 7. Electrical and mechanical work are ongoing. Underground...

Construction Update 01-17-20
Park District The Abbot Drywall work continues on levels 5 and 6, with MEP rough-ins on levels 7, 8 and 9. Masonry work continues along...

Construction Update 01-03-20
Park District The Abbot Slab on metal deck on level 12 north was completed today (01/03). Setting of load bearing wall panels and joists...

Construction Update 12-20-19
Park District The Abbot Mechanical, electrical and plumbing work is underway on levels 5 and 6. Drywall is being installed on level 4. ...