MSUFCU Construction Updates 8-26-2022

The mechanical and plumbing contractor is currently onsite installing overhead piping. The HVAC contractor is also onsite installing duct work and overhead mechanical units. The framing contractor has completed the envelope on the east side and the eastern half of the south side and will move to the western half of the south elevation once the east elevation is complete. The framing contractor will also have a crew working on interior wall layout and framing. The mason will begin brick work on the east elevation soon. Slab on grade has been completed. As we complete more of the exterior we will begin interior drywall and inwall rough in of MEP.
Eastbound Albert Ave. has been reopened to through traffic. The lane closures on Abbot Rd. will remain in effect for the foreseeable future. The south access to the alley off Albert Ave. will be closed to vehicles and pedestrians for the duration of overhead work to help ensure safety. The alley is accessible from the north.