November 15, 2019

West Grand River Ave. Underground Utility Work and Lane Closures Beginning Monday (11/18)

Project Map

Due to weather delays the week of 11/08/19, the underground utility work did not take place.  The underground utility work is scheduled to begin on Monday (11/18) in the...

November 8, 2019

West Grand River Ave. Underground Utility Work and Lane Closures Beginning Monday (11/11)

Underground utility work will continue in the 100 block of west Grand River Ave. on Monday, (11/11).  The following lanes closures will be in effect starting at Abbot Road.

...

November 1, 2019

Underground Utility Work – Abbot Rd. and Albert Ave.

The underground utility work at the intersection of Abbot Rd. and Albert Ave. should be concluding early this evening.  Abbot Road and Albert Ave. will re-open to traffic.

West Grand River Ave. Underground Utility Work...

October 29, 2019

Beginning Friday, November 1, underground utility work will begin at the intersection of Albert Ave. and Abbot Road and this intersection will be closed to through traffic.  This closure requires the following traffic detours:

Abbot Rd., from Grand River to Albert Ave....

October 25, 2019

Park District

The Abbot

This week, wall panels continued to be placed on level 8.  Joisting and decking for level 9 will follow with the first level 9 pour expected to occur next week. The tower crane has been re-inspected and is back in service on the South core, which...

October 18, 2019

Park District

The Abbot

Concrete pours continue along with wall framing, mechanical, plumbing and electrical work.  Underground infrastructure work at the south end of Evergreen Ave. is  tentatively scheduled to begin on Monday (10/21).  The underground utility work at E...

October 11, 2019

Park District

The Abbot

Work is underway for the Level 8 deck concrete pour.  Masonry work is progressing on the ground level.  Wall framing, elevator work and the installation of the exterior skin on level two and three is underway.   Work on the covered pedestrian walk...

October 4, 2019

Park District

The Abbot

The Level 7 deck has been completely poured and wall panels are now being erected.  Framing of exterior walls on level 1, 2 and 3 is underway.  Next week the concrete pad for the buck hoist will be poured.  Work on the covered pedestrian walkway a...

September 27, 2019

Park District

The Abbot

The south half of the Level 7 deck has been poured, while the Level 7 North panels and joists are nearly complete and being prepped for a pour on Monday (9/30). Rebar has been installed on the North Core. The North Core will be detailed, closed, a...

September 13, 2019

Park District

The Abbot

At the Abbot, the contractor is currently working on the L6 deck. The work should be completely finished and poured out early next week. The north and south cores, L9-L10, will pour next week as well.  Underground plumbing and electrical piping ar...

Please reload

Please reload

Recent Posts
Featured Posts

Construction Update 11-15-18

November 15, 2019

1/10
Please reload

Blog