MSUFCU Construction Update 7-29-2022
The mechanical and plumbing contractor is currently onsite installing overhead piping. The HVAC contractor is also onsite installing duct...

MSUFCU Construction Update 7-22-2022
The mechanical and plumbing contractor is currently onsite working on layout and installing storm piping on the 7th floor. The HVAC...

MSUFCU Construction Updates 7-15-2022
The mechanical and plumbing contractor is currently onsite working on layout and installing storm piping on the 7th floor. The HVAC...

MSUFCU Construction Update 7-8-2022
The mechanical and plumbing contractor is currently onsite working on layout and installing storm piping on the 7th floor and roof. The...

MSUFCU Construction Update 7-5-2022
Steel deck installation has been completed and the iron workers are finishing the final detailing and miscellaneous structural items. The...

MSUFCU Construction Update 6-27-2022
Steel erection is complete and we are breaking down and removing the crane from the site. Steel deck is being installed on the remaining...

Construction Updates 6-3-2022
East Lansing Parking Facility Repairs Project The East Lansing Parking Facility Repairs Project continues in Division Street Garage....

MSUFCU Construction Update 5-27-2022
Installation of the final third of the building structural steel is in-progress, with an expected completion date of early June. The...

Construction Updates 5-20-2022
East Lansing Parking Facility Repairs Project The East Lansing Parking Facility Repairs Project continues in Division Street Garage....

MSUFCU Construction Update 5-16-2022
Structural steel erection of the center third of the building is ongoing in conjunction with the north precast wall infill. Precast...