January 31, 2020

Park District

The Abbot

Drywall work continues on level 6 moving up to level 7.  Electrical and mechanical work are ongoing.  Underground utility work will be completed the week of 02/03.  The covered pedestrian walk-way along Grand River Ave. is open.  The project is on...

January 22, 2020

Park District

The Abbot

Drywall work continues on levels 5 and 6, with MEP rough-ins on levels 7, 8 and 9.  Masonry work continues along with the underground utility work.  The storm sewer work was completed this week with the water main work wrapping up by Tuesday (01/2...

January 3, 2020

Park District

The Abbot

Slab on metal deck on level 12 north was completed today (01/03).  Setting of load bearing wall panels and joists on level 12 south is underway.  Exterior window installation is in progress on levels 7 and 8. Mechanical, electrical and plumbing wo...

December 20, 2019

Park District

The Abbot

Mechanical, electrical and plumbing work is underway on levels 5 and 6.  Drywall is being installed on level 4.  Wall panel installation is underway on Level 12. Framing, window installation and masonry is ongoing.  A concrete pour will take place...

December 12, 2019

Park District

The Abbot

The last core pour is scheduled to be completed on Monday (12/16).  Level 4 interior wall framing, and in-wall MEP rough ins are complete and drywall installation will begin on Monday (12/16).  Load bearing walls are being set onto Level 11 and wi...

December 6, 2019

Park District

The Abbot

Installation of the wall panels on level 10 has been completed.  Drywall installation on level 4 will begin early next week (12/09).  Mechanical, Electrical and Plumbing trades are on site along with the Masonry contractors.  Underground utility w...

November 27, 2019

Park District

The Abbot

Installation of the wall panels on level 10 is finishing up.  Mechanical, Electrical and Plumbing trades are on site along with the Masonry contractors.  Installation of windows for level 4, 5 and 6 will begin the week of 12/2.  Concrete pours wil...

November 22, 2019

West Grand River Ave. Underground Utility Work Completed

The contractor has finished the underground utility work and the west bound lanes of Grand River Ave. are now open.

Park District

The Abbot

This week concrete pours, wall framing, and window installation continue to...

November 15, 2019

West Grand River Ave. Underground Utility Work and Lane Closures Beginning Monday (11/18)

Project Map

Due to weather delays the week of 11/08/19, the underground utility work did not take place.  The underground utility work is scheduled to begin on Monday (11/18) in the...

November 8, 2019

West Grand River Ave. Underground Utility Work and Lane Closures Beginning Monday (11/11)

Underground utility work will continue in the 100 block of west Grand River Ave. on Monday, (11/11).  The following lanes closures will be in effect starting at Abbot Road.

...

Please reload

Please reload

Recent Posts
Featured Posts

Construction Update 01-31-20

January 31, 2020

1/10
Please reload

Blog