Construction Update 03-29-19
Park District Pile caps and grade beams were installed this week. The Building permit was issued, and the project is expected to go...
Construction Update 03-22-2019
Park District Concrete pours and forming for beams for the stair cores and elevator pits took place this week. Plans are underway for...
Water Main Installation - Abbot Road Lane Closures and Alley Closure Beginning Next Week
SMLXL Beginning Monday, March 25, a water main replacement project related to the Center City District redevelopment project will be...
Construction Update 03-15-19
Park District Work is complete on the auger cast piles, and transitioning to forming the concrete caps for the piles. Work to prepare the...
Construction Update 03-08-19
Park District On the Albert/Grand River portion, the BWL duct bank removal/ replacement project has completed, as well as the removal of...
Construction Update 03-01-19
Park District On the Abbot/Grand River building, the auger cast pile work has proceeded well, with all piles expected to be cast next...