Construction Update 08-23-19

Park District

On the corner building, cold-form steel continues to be installed. The south stair core is poured to the 8th level and the north core is complete to the 7th floor. Concrete pours for level 5 are expected to begin in late August.


The Board of Water and Light will be removing (3) power poles on Evergreen Ave. Once that work is completed the underground utility work will begin along with the closure of Albert Ave. he tentative start date for the underground utility work and closure of Albert Ave. is early September.


On the hotel site, the project continues to go vertical, as underground work is well underway along with work to pour the slab-on-grade concrete.

Center City

The 12 story Landmark building is mostly complete with move-ins underway.


The 10 story Albert Ave. building has finishes in various stages on the upper floors. Exterior skin is nearing completion in the next week with balcony installation following close behind. The parking deck is open and accessible to the public. Work on Albert Ave. continues while all paving and hardscapes are substantially completed. Landscaping, planters and tree installation is mostly complete. Tenant spaces on the ground level are progressing with various general contractors completing this work.

The Hub @ East Lansing

The TCO was issued on Wednesday (08/21). The contractor is finishing up the work on the amenity deck. Once the water main project in the alley is completed, the alley, along with the parking lot, will be paved.


Thank you for your patience during the construction downtown. Please remember to sign up for downtown East Lansing construction alerts by texting ELBUZZ to 38470. You can also visit www.EastLansingBuzz.org to find the latest information about the construction in downtown East Lansing. As always, you can reach the City Construction Communication Team at construction@cityofeastlansing.com or (517) 319-6930 with any questions.