Water Main Service Connections on 06-08-19

On Saturday, June 8, at the east end of the 100-200 block of E. Grand River Alley, the contractor will be completing the final water service connections to the new water main. To minimize the disruption to residents and businesses, this work will occur in the early morning hours beginning at 4 a.m. until 11 a.m.

This work will affect water service to all of the businesses and residents for approximately one hour in the following buildings.

211 E. Grand River Ave.

213 E. Grand River Ave.

217 E. Grand River Ave,

219 E. Grand River Ave.

225 E. Grand River Ave.

233 E. Grand River Ave.

203-209 M.A.C. Ave.

205 M.A.C. Ave.

207 M.A.C. Ave.

209 M.A.C. Ave.

211 M.A.C. Ave.

221 M.A.C. Ave.

The work will begin at 211 E. Grand River Ave., and will continue east to M.A.C. Ave.

If all the water service connections are not completed on Saturday (06/08), the work will be completed on Monday (06/10). The work hours will begin at 4 a.m.

East Lansing Department of Public Works staff will be on site throughout the project. City staff has visited businesses affected by the water service connections.

Thank you for your patience during the construction period. Please remember to sign up for downtown East Lansing construction alerts by texting ELBUZZ to 38470. You can also visit www.EastLansingBuzz.org to find the latest information about the construction in downtown East Lansing. As always, you can reach the City Construction Communication Team at construction@cityofeastlansing.com or (517) 319-6930 with any questions.