MSUFCU Construction Updates 4-29-2022


Structural steel erection of the center third of the building is ongoing in conjunction with the north precast wall infill. The crane has been moved slightly to the west to allow for the erection. The mechanical and plumbing contractor is currently on-site working on layout and installing hangers for the fourth floor overhead mechanical and plumbing. Beginning late next week, we will grade and complete earth work for the first floor to prepare for MEP (mechanical, electrical, and plumbing) underground to begin on the following week. The first concrete pour is scheduled to take place on May 18.

The lane closures on Abbot Rd. and Albert Ave. will remain in effect for the foreseeable future. The south access to the alley off Albert Ave. will be closed to vehicles and pedestrians for the duration of overhead work to help ensure safety. The alley is accessible from the north.