MSUFCU Construction Update 5-6-2022

Structural steel erection of the center third of the building is ongoing in conjunction with the north precast wall infill. The mechanical and plumbing contractor is currently on-site working on layout and installing hangers for the fourth and fifth floor overhead mechanical and plumbing. Beginning early next week, we will grade and complete earth work for the first floor to prepare for MEP (mechanical, electrical, and plumbing) underground to begin immediately after. The first concrete pour is currently scheduled for May 20. We will install loading platforms from the third through seventh floors at the end of May.
Starting May 16, Albert Ave. will be closed to through traffic between Abbot Rd. and the Abbot Apartments garage entrance. This closure is to facilitate our second crane placement. This closure will be in effect for the summer and is expected to be removed prior to MSU student move in. The lane closures on Abbot Rd. will remain in effect for the foreseeable future. The south access to the alley off Albert Ave. will be closed to vehicles and pedestrians for the duration of overhead work to help ensure safety. The alley is accessible from the north.