top of page

MSUFCU Construction Update 10-01-21

MSUFCU

City of East Lansing DDA Properties – 314, 328, and 334 Evergreen

Permanent fencing and power to the construction trailer is currently being installed. DDA Site lighting and power will be established next week.

MSUFCU East Lansing Building Located at 311 Abbot

The earth retention system is currently being installed and is on schedule to be completed by the end of this week. Site demolition will take place at the end of this week and continue throughout the end of next week. Grade establishment and deep foundations are scheduled to start in the next few weeks.


Thank you for your patience during the construction downtown. Please remember to sign up for downtown East Lansing construction alerts by texting ELBUZZ to 38470. You can also visit www.EastLansingBuzz.org to find the latest information about the construction in downtown East Lansing. As always, you can reach the City Construction Communication Team at construction@cityofeastlansing.com or (517) 319-6930 with any questions.




Comments


Featured Posts
Recent Posts
bottom of page