Construction Updates 3/11/22

MSUFCU East Lansing

Precast installation is currently on hold while frost laws are in effect. Structural steel erection has begun on the east side of the building. The steel will be built up to the roof on the east side before moving to the west. Steel erection will continue through April 2022 with expected completion in early May. The mason is on-site installing granite on the north side of the building. Consumers Energy will be on-site next week to install the gas meter. This work will take place within the fenced construction portion of the alley. The fence along Albert Ave. towards Evergreen Ave. has been reworked to allow relocation of the crane at the corner of the alley and Albert Ave. The fire suppression contractor will be on-site installing a temporary fire suppression system standpipe in the east stair shaft next week. Underground mechanical and electrical will recommence at the end of March, with the first slab-on-grade concrete pour taking place in early April.

The lane closure on Abbot Ave. has been reinstated and will remain in effect for the foreseeable future. The westbound lane closure on Albert Ave. has been installed and will remain in effect for the foreseeable future.

The south access to the alley off Albert Ave. will be closed to vehicles and pedestrians for the duration of overhead work to help ensure safety. The alley is accessible from the north.

Featured Posts
Recent Posts
bottom of page