Construction Update 01-31-20

Park District


The Abbot


Drywall work continues on level 6 moving up to level 7. Electrical and mechanical work are ongoing. Underground utility work will be completed the week of 02/03. The covered pedestrian walk-way along Grand River Ave. is open. The project is on schedule to be topping out mid-February.


The Graduate Hotel


Mechanical, electrical and plumbing rough-ins continue on levels 1 and 2. Concrete pours on level 4 were completed this week.


Thank you for your patience during the construction downtown. Please remember to sign up for downtown East Lansing construction alerts by texting ELBUZZ to 38470. You can also visit www.EastLansingBuzz.org to find the latest information about the construction in downtown East Lansing. As always, you can reach the City Construction Communication Team at construction@cityofeastlansing.com or (517) 319-6930 with any questions.