2-4-2022 Construction Updates

MSUFCU East Lansing Building at 311 Abbot Rd.

Steel and precast panels on the north elevation of the building are currently being installed. Trucks will be arriving daily with loads of precast panels and steel. The lane closure on Albert Ave. will be used to take the deliveries, but there is potential for trucks to be backed up on Evergreen Ave. as the panels are being installed. This will continue through April 2022 with expected completion in early May.

The lane closure on Abbot Rd. has been reinstated and will remain in effect for the foreseeable future. The westbound lane closure on Albert Ave. has been installed and will remain in effect for the foreseeable future.

The south access to the alley on Albert Ave. will be closed for the duration of the steel and precast erection.