Construction Updates 3/11/22
MSUFCU East Lansing Precast installation is currently on hold while frost laws are in effect. Structural steel erection has begun on the...
Construction Updates: 3-07-2022
MSUFCU East Lansing Building Located at 311 Abbot Precast on the east tower is finished. Precast installation will be paused until frost...
Construction Update 02-18-22
MSUFCU East Lansing Building Located at 311 Abbot Steel and precast panels on the north elevation of the building are currently being...
2-4-2022 Construction Updates
MSUFCU East Lansing Building at 311 Abbot Rd. Steel and precast panels on the north elevation of the building are currently being...
Construction Updates 1-28-2022
MSUFCU East Lansing Building Located at 311 Abbot Installation of the exterior concrete, foundations, and walls are as complete as can be...
1-14-2022 Construction Updates
MSUFCU East Lansing Building at 311 Abbot Rd. Installation of the exterior concrete foundations and walls is ongoing with installation of...