MSUFCU Construction Update 5-27-2022
Installation of the final third of the building structural steel is in-progress, with an expected completion date of early June. The...

Construction Updates 5-20-2022
East Lansing Parking Facility Repairs Project The East Lansing Parking Facility Repairs Project continues in Division Street Garage....

MSUFCU Construction Update 5-16-2022
Structural steel erection of the center third of the building is ongoing in conjunction with the north precast wall infill. Precast...

MSUFCU Construction Update 5-6-2022
Structural steel erection of the center third of the building is ongoing in conjunction with the north precast wall infill. The...

MSUFCU Construction Updates 4-29-2022
Structural steel erection of the center third of the building is ongoing in conjunction with the north precast wall infill. The crane has...

MSUFCU Construction Updates 4-14-2022
Installation of the precast resumed on the west tower, which is expected to be completed on Wednesday, April 20. The north precast wall...

MSUFCU Construction Update 04-08-22
We will restart the precast installation on Monday, April 11, starting with the west tower. The west tower is expected to be complete by...

Construction Update April 1, 2022
We anticipate recommencing on the precast installation on Wednesday, April 6, starting with the west tower. The west tower is expected...

Construction Updates: 3-25-2022
MSUFCU East Lansing Building Located at 311 Abbot Precast installation is currently on hold while the spring thaw road weight...

Construction Update 03-18-22
Precast installation is currently on hold while the spring thaw road weight restrictions are in effect. Structural steel erection is...