Downtown Construction Update 5-18-18
CENTER CITY Significant progress was made on the Albert Avenue underground utility work this week. As noted, Abbot Road was closed for...
***Upcoming Abbot Road Closures & Overnight Work***
CENTER CITY Upcoming Abbot Road Closures & Overnight Work The Center City water and sewer portion of the infrastructure work currently...
Downtown Construction Update 5-11-18
Center City Board of Water and Light Overnight Work **Please note, weather permitting, some late night/ early morning work is expected to...
Night Crane 5/14 and Albert Closure Today
The Hub @ East Lansing – Night Work Postponed Night work to install the tower crane has been delayed one week, and is now anticipated to...
Downtown Construction Update 5-4-18
Center City Progress has continued this week, as the project continues to go vertical. Work has commenced on the third story as...
Center City Update 5-2-18
Board of Water and Light Overnight Work **Please note: Some late night/ early morning work is expected to occur between the hours of...